Innovation and technology development is a dominant global trend. The Government has been encouraging the construction industry to adopt new technologies. Under the ongoing implementation of the Kai Tak Development (KTD), the Civil Engineering and Development Department (CEDD) is now constructing a pedestrian subway linking Shing Kai Road and Choi Hung Estate to facilitate pedestrian access between Kai Tak and its neighbourhood. The project has introduced the Rectangular Tunnel Boring Machine (RTBM) technology for the first time to enhance works safety and efficiency. Recently, the boring works have been successfully completed and I have attended the breakthrough ceremony of the subway. In this blog, colleagues of the CEDD will share with us this new technology and how to use it to overcome various challenges of the project.
The project is challenging
The pedestrian subway has a total length of 140 metres, with a height of 2.8 metres and a width of 3.9 metres. Project Manager of the East Development Office of the CEDD, Mr LEUNG Chung-lap, Michael, says the subway passes through the busiest traffic routes in East Kowloon, such as the flyover of the Kwun Tong Bypass and Prince Edward Road East. It also has to weave around the piles of the flyover without affecting its foundation structure, and pass closely through major underground utilities, including large-scale stormwater box culverts, district cooling system pipes, large diameter sewers and fresh water pipes, as well as high voltage power lines. The project is, therefore, full of challenges.
Introduction of the first RTBM
Mr Michael LEUNG says the conventional tunnelling method of installing temporary support while excavating on-site is associated with relatively high risks. After detailed consideration, the CEDD has decided to introduce the first RTBM to Hong Kong for the project. The new technology is wholly operated by mechanical means to eliminate manual digging, enhance works safety and improve the working environment while it can also reduce the impacts of excavation works on surrounding facilities. Besides, since the tunnel segments are prefabricated off-site, it not only enhances the quality and efficiency but also saves the construction time needed.
90-tonne cutterhead to bore into the subway
Regarding the subway boring process, the CEDD’s Senior Engineer, Mr CHU Chi-hong, Keith, says the workers are to first construct a launching shaft for the installation of hydraulic jacks, a cradle and the RTBM. After that, the prefabricated tunnel segments are hoisted individually into the launching shaft and placed on the cradle therein. The hydraulic jacks would then push each segment forward until it is up against the previous one already in place in the boring machine. Meanwhile, the cutterhead of about 90 tonnes, which is equivalent to the total weight of about four fully loaded double-decked buses, started to operate and bore forward. This procedure repeats until the cutterhead has reached the receiving shaft at the other end of the tunnel.
Computerised Auto-control System
Mr Keith CHU tells us that the whole tunnelling system is equipped with a computerised control system. The system monitors the speed of the RTBM’s main cutter disk and four auxiliary cutter disks, the propulsion speed of the hydraulic jacks, as well as directional positioning and earth pressure balance on a real-time basis throughout the process, thereby preventing ground loss and seepage during excavation to ensure the surrounding facilities are not affected by the works. The entire subway is formed by 92 segments, each weighing about 30 tonnes. These tunnel segments are prefabricated at the yard set up by the CEDD at Muk On Street adjacent to the site for easier transportation, better productivity and enhanced quality.
Linking the past with the future
Following the successful excavation works, the entire subway is scheduled for completion in the middle of next year. It is really encouraging to know that the next project, a pedestrian subway linking the KTD to Kowloon City, will also apply the RTBM technology. Construction has also begun recently. The experience gained from this first use of the RTBM will serve as good reference for the new project.
I hope to see more construction projects using RTBM technology in Hong Kong to realise multiple benefits. I also hope that this successful experience will encourage wider adoption of innovative technologies in the industry to tie in with the Government’s policy “Construction 2.0”, which strives to push ahead “Innovation” and “Professionalisation” in project implementation to enhance the construction industry in Hong Kong.
Early recovery of the construction industry
Furthermore, I would like to take this opportunity to reiterate that the Government will continue to work hard to help the pandemic-affected local construction industry to recover early. A number of measures to support the construction industry have been introduced under the first two rounds of Anti-epidemic Fund, providing cash subsidy directly to workers and enterprises to support enterprises and safeguard jobs. The Development Bureau, along with all works departments, will continue to make greater efforts to implement works projects of various sizes that will benefit the community. We will also further streamline the approval process to give an early start to private development projects that comply with legal requirements, which will create more job opportunities for workers. Besides, the Buildings Department and the Urban Renewal Authority will accelerate the implementation of “Operation Building Bright 2.0” to offer assistance to more owner-occupiers of old buildings in need of repair and maintenance, and benefit medium- and small-sized contractors and workers who provide the services.
It is worth mentioning that, in the next few years, the annual capital works expenditure is expected to reach $100 billion on average. In the short to medium term, as at July this year, the Legislative Council had endorsed a total of more than $170 billion in capital works funding in the 2019/20 legislative session, with over 60 percent of the projects already in progress. Tendering procedures have also been initiated for the remaining projects. With these projects coming on line, we expect the employment situation of the construction industry to further improve.
Please click on the image above to watch the video.
The Secretary for Development (SDEV), Mr WONG Wai-lun, Michael, addressed the ceremony for successful breakthrough of the first Rectangular Tunnel Boring Machine (RTBM) in Hong Kong held earlier (23 October).
The SDEV, Mr Michael WONG (centre), the Permanent Secretary for Development (Works), Mr Lam Sai-hung (third right), the Director of Civil Engineering and Development, Mr LAU Chun-kit, Ricky (third left), Project Manager of the East Development Office (EDO) of the Civil Engineering and Development Department (CEDD), Mr LEUNG Chung-lap, Michael (first left), and representatives of the project consultant and contractor attend the breakthrough ceremony, marking a new milestone in tunnel construction.
Project Manager of the EDO of the CEDD, Mr Michael LEUNG, says that the subway project linking the Kai Tak Development (KTD) and Choi Hung Estate passes through the busiest traffic routes in East Kowloon and passes through major underground utilities. To effectively control the risks, the project team has introduced the first RTBM to Hong Kong for the project.
The CEDD’s Senior Engineer, Mr CHU Chi-hong, Keith, says that the subway will be formed by 92 prefabricated segments., and a prefabrication yard is set up near the launching shaft for easier transportation of segments.
The pictured cutter head of the RTBM, weighing about 90 tonnes, is made up of a main cutter disk and four auxiliary cutter disks.
After installing the hydraulic jacks, the cradle and the RTBM in the launching shaft, the workers put inside the prefabricated tunnel segments one by one. The boring machine and the hydraulic jacks then push the whole series of segments forward gradually until reaching the receiving shaft at the other end of the tunnel.
The prefabricated segments not only constitute the permanent structure, but also remove the need to install temporary earth support during construction, thereby reducing construction risks.
The RTBM is wholly operated by remote mechanical means.
Thanks to the hard work of the project team, the excavation works of the Kai Tak to Choi Hung pedestrian subway project have been completed successfully.